In recent years, IBM has upgraded their columbus data facility to tier iv standards, requiring dual feed redundancy throughout the entire system. The superior group team provided the original build facilities for the facility and provided the services for the dual power upgrade on a design assist basis. The dual power upgrade was completed in an operating facility, requiring complex planning and methods of procedure.

  • Contract: $8M
  • New 15kv service
  • 5000 kva ups
  • New paralleling switchgear