Progressive Insurance Data Center

Progressive Insurance built their Cleveland corporate data center in 2001 to tier iv standards, making it one of the first tier iv facilities in ohio. The complex underground layout was completed design build with a fast-track schedule. The project was delivered on time and within budget.

  • GMP: $8M
  • Paralleling Switchgear 8000 kw Generator
  • 3000kw UPS
  • Over 300,000’ of 500 – 750mcm cable

Project URL: /project-gallery/mission-critical/progressive.php

Image URL: http://bd99954ed08d3c16619b1d4422f0e622c96d1667.gripelements.com/images/project-gallery/mission-critical/progressive.jpg

Image Title: Progressive